This project consisted of the phased removal of the existing Port Hardy Airport terminal building and the construction of the new one, to meet sustainable building standards on the same site. The airport remained operational for the duration of construction. The first phase of this contract included site preparation, demolition, and hazardous waste remediation of the existing building with select materials being recycled and reused. The next phase consisted of the construction of the new terminal building without impeding airport operations and in coordination with Airport Management and the relocation of airport operations by transferring and reinstalling all equipment, furniture, and fixtures from the temporary facilities to the new building, completing wayfinding and exterior signage and reinstating all parking and exterior public areas.
Finally, the last phase comprised the decommissioning and removal of the temporary facilities and restoration of the area.