This project was completed in three phases over eighteen months, to allow the existing school to remain occupied and in use. During the summer months, critical path work as fast-tracked to provide minimum impact to the fully operational school activities.
Demolition of the existing south classroom wing to allow for the construction of a new 4,175 m2 addition, consisting of multi-purpose room, media-tech room and a two storey classroom block. Seismic upgrading & renovations to the north wing, consisting of general offices, gymnasium and the incorporation of new change rooms